Here’s one way to curb soaring energy costs: roll out virtual power plants. Utility VPP programs could slash residential bill increases by more than half, according to a new Brattle Group report ( ...
Hold onto your hats: Between Jan-Sep 2026, average monthly wind generation was 68% higher than over the same period last year. Those nine months brought 4.6 GWh of wind generation, slightly higher ...
In August, PJM filed its Interim Resource Adequacy Service (IRAS) proposal to bring data centers and other new large loads onto the grid. Now, FERC is back with some (harsh) feedback… The no’s: FERC ...
Brrr: Xcel Energy has proposed freezing its Minnesota electric base rates for two years, pending approval from the Minnesota PUC. How? Xcel would draw on federal tax credits from planned energy ...
In Australia has abundant sunshine, but generating solar electricity is only part of the challenge. Homeowners also need to understand when their systems produce power, when their households consume ...
The end game may be emerging in the enormous and controversial proposed merger of Virginia-based Dominion Energy and Florida’s Next Era Energy. Announced in mid-May, the companies bill it as creating ...
For over a century, grid operators have used an evolving set of technologies to manage power flows across the transmission system. From reactors and capacitors to phase-shifting transformers (PSTs) ...
On July 22, 2026, approximately 3,800 MW of data center load unexpectedly disconnected from PJM’s grid in Northern Virginia following a transmission fault. The facilities transferred to backup ...
New numbers: As part of President Trump’s strategy to accelerate data center permitting, he’s turning to federal lands in the West. The Bureau of Land Management is reviewing ”far more” data ...
Meanwhile, on a different coast: New York state is moving towards its clean energy goals with new funding for eight bulk energy storage and 13 large-scale renewable projects. Combined, they’re set to ...
Why? Amazon is developing 44 GW of data centers, fast. In the past year, the hyperscaler nearly doubled its data center capacity in the US, according to a new Cleanview report. And it needs a lot of ...
Deadline approaching: Grid operators have until mid-November to tell FERC how they’re going to seamlessly bring new large loads onto the grid. The latest: CAISO’s draft proposal centers on “proactive ...
Some results have been hidden because they may be inaccessible to you